Modernization of Control & Protective Systems of the Elefsis Refinery Existing Units

Modernization of Control & Protective Systems of the Elefsis Refinery Existing Units

Client:
HELLENIC PETROLEUM S.A. - ELEFSIS INDUSTRIAL COMPLEX
Status:
Completed
Country:
Greece
Business Area:
Oil
Solution/Service:
Studies,Project Management Services,Technical Consulting
Completion Year:
2013
Category:
Refineries

Technical Data

  • Distributed Control System (DCS)
  • Emergency Shutdown System (ESD)
  • Fire & Gas Detection System (FGS)

Our Services

  • Detail Design of DCS/ESD & FGS for all existing Units of the refinery and part of utilities units
  • Integration of existing to new automation systems
  • Factory Acceptance Tests (FAT)
  • Site Acceptance Tests (SAT)
  • Commissioning and Start-Up of the DCS/ESD & FGS
  • Owner’s engineer and consultancy for all the automation systems of the Elefsis Refinery Upgrade

Description

Detail design of the Central Automation Systems (DCS/ESD/FGS) of HELPE Elefsis Refinery up to commissioning and start-up phase. The activity was carried out by senior engineers of the Instrumentation & Automation discipline which were involved during the engineering phase of the Units revamp.