High Pressure Natural Gas Pipeline - Stefani, Varnavas, Aliveri
High Pressure Natural Gas Pipeline - Stefani, Varnavas, Aliveri
Client:
HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A. (DESFA S.A.)
Business Area:
Environment,Natural Gas
Solution/Service:
Studies,Project Management Services,Technical Consulting
Category:
High & Medium Pressure, Compressor Stations, Metering and Regulating Stations, Permit Engineering, Environmental Consulting Services
Technical Data
- Size / Length: 20” / 72 km (14,2 offshore)
- 5 Scraper and Block Valve Stations
- 2 Metering Stations
Our Services
- Stakeholders Engagement and Permits Acquisition
- Basic and Detailed Design
- Specialized Seismic Studies
- Safety Studies
- Environmental Impact Studies (Preliminary and Final Environmental Impact Assessment)
- Special Logging Studies
- Construction Management and Construction Supervision Services
- Contract Administration Services
- Quality Services
- Experts’ Report in the High Court
- Close out Activities
- Final Documentation packages
Description
High Pressure Natural Gas of Stefani-Varnavas-Aliveri was a very demanding project regarding social licensing and acceptance. The pipeline passes through very valuable lands in the regions surrounding Attica. ASPROFOS was engaged from the very beginning through the technical design of the project and also its environmental and social licensing. Construction supervision, in collaboration with ILG, of the offshore section is also a highlight, given that it was the first High Pressure Natural Gas Pipeline constructed in Greece.