FEED for three (3) Flare Gas Recovery units at MAA Refinery

FEED for three (3) Flare Gas Recovery units at MAA Refinery

Client:
KUWAIT NATIONAL PETROLEUM COMPANY
Status:
In Progress
Country:
Kuwait
Business Area:
Oil
Solution/Service:
Studies
Completion Year:
-
Category:
Refineries

Technical Data

The Project scope includes developing of FEED package for the following new Flare Gas Recovery Units

  • Refinery New Flare Gas Recovery Unit
  • High Pressure Gas Plant Flare Gas Recovery Unit
  • Gas Plant Acid Gas Recovery Project Flare Gas Recovery Unit

Our Services

  • Front End Engineering Design
  • Project Budget and Cost Estimation
  • Project Management Services

Description

The objective of this study is to:

  • estimate flare loads and composition from various flares for non-emergency flaring case
  • decide flare grouping and determine optimal capacity and location of new flare gas recovery units so as Kuwait National Petroleum Company can achieve goal of zero non-emergency flaring
  • identify bottlenecks of New-Flare Gas Recovery Unit (U-105) according to the studies conducted for routing of acid gases to existing Sulphur block in refinery area and
  • evaluate available alternative Flare Gas Recovery Unit technologies and option selection
    ASPROFOS should prepare the documents that define the Project Basic requirements and perform FEED, so that the project requirements are well defined with scope clarity and EPC Contractor can submit the LSTK (Lump Sum Turn Key) bid with a reasonable margin. During FEED, details for each of the Project Scope of Works shall be developed to a level that will be sufficient to allow the selected EPC Contractor to conduct detailed engineering work, develop a detailed execution plan, estimate, and schedule other EPC activities to be conducted during the implementation phase.
    The Project Scope of Services comprises of the following:
  • Preparation of FEED documents
  • Preparation of ITB documents for EPC works.
  • Development of EPC Cost & EPC Schedule.
  • Preparation of Stage Gate Documents for FEED Stage Gate Closure.
  • Obtaining approvals from Government bodies/ Statutory Authorities