The existing equipment and piping, including valves and instruments will be replaced with new. The new equipment and piping must be suitable for Diesel with high content of sulfur and increased temperature conditions. It will be replaced two pumps and their respective suction & discharge circuits, two tubes side (for one the new beam should be specified taking into account the design pressure requirement) and two Strippers.
The project scope included detailed engineering for the thermal uprating of CDU lV circuits.